Given the permanent digging and demolishing in Yung Shue Wan, here the good practice measure proposed in this matter (as attachment) and an excerpt from an e-mail conversation with the EPD. If the private DIY'ers do not care, at least the contractors of the Drainage Department should.
Greetings,
Marcus
--------------------
Dear Mr. Diu,
thank you again for your information.
I understand that there is no noise level in force for construction work during permitted times. Unfortunately, I find that there are works going on which do not even apply easy noise mitigation measures (like closing windows etc.) and some anti-social individuals even try to be "as noisy as possible" to show off that they have the right to do so - which seems to be right under Hong Kong regulations.
I have seen a lot of noise reduction measures proposed on your web site, which are all very good. Do you recommend a way to encourage the contractors to apply such measures?
Greetings,
Dr. Marcus Schütz
--------
http://web.me.com/marcus_schuetz/Site/Blog/Blog.html
END
On 26 Jun 2009, at 8:21 PM,
pdiu@epd.gov.hk wrote:
Dr. Marcus Schütz
Thank you for your email enquiry dated 25.6.09 below.
2. Please note that noise from construction sites in Hong Kong is
subject to control under s.6 of the Noise Control Ordinance (Cap. 400).
Powered mechanical equipment for the purpose of carrying out any
construction work other than percussive piling should not be used between
the hours of 7 p.m. and 7 a.m., or at any time on a general holiday without
a valid construction noise permit [s. 6(1) refers].
3. If the use of powered mechanical equipment for carrying out any
construction work other than percussive piling is between the hours of 7
a.m. and 7 p.m. of normal weekdays (ie Mon to Sat), there is no specified
noise limit under the Noise Control Ordinance.
4. I hope the above can address your enquiry. Should you have further
enquiry, you can call me at 2516 1782.
peter Diu
EPD
Regional Office (South)
26.6.2009
EP 748/C1/3